Home Forums Discussion Resource Utilization on MS2013 Reply To: Resource Utilization on MS2013

#247461
Karlene Ward
Guest

From the
From the Gantt Chart view, go to the Task tab turn on Details (it’s in the Properties Group). So you see the details form in the lower half of your screen. Remove the resource allocation you have now, using the form, click OK. Reassign the resource using the Details Form, in the Units field put 25% and then choose OK. This will make the assignment a flat contoured assignment – ie spread the work evenly over the duration.