Reply To: Effective Resourcing Management in Ms Project 2013 – A Case Study (Help needed)

Home Forums Discussion Effective Resourcing Management in Ms Project 2013 – A Case Study (Help needed) Reply To: Effective Resourcing Management in Ms Project 2013 – A Case Study (Help needed)

#268352
Kumar
Guest

Nico

thanks for the reply. Yes u r correct on Jan 7th case. But, still my expectation would be
Expectation:
On Jan 7th, 2015 – i expected all 3 resources work. Hence total hours is 4+4+2 = 10 hrs
On Jan 8th, 2015 – Since resource3 cant work, Resource1 and Resoure2 will work 4+4 = 8 hrs
On Jan 9th, 2015 – Since resource3 cant work, Resource1 and Resoure2 will work 3+3 = 6 hrs
So i would expect the work to be showing as completed by Jan 9th. But it shows project will complete by Jan 13th only !

I expect project should complete by Jan 9th itself, with resource 1 using 4+4+3 = 11 hrs, resources2 also using 11 hrs and resource 3 using 2 hours only ! But i am not getting this result.

Please assist. I am using microsoft project 2013 software.

Kumar