Home › Forums › Discussion › 99% completed project when all tasks are 100% › Reply To: 99% completed project when all tasks are 100%
I have seen this and have found a solution, although I don’t understand the reason it is occurring. If you look at the “Actual Finish” field it shows as N/A. If you set this date the 99% changes to 100%.