Loading...
Quick Links

Reply To: 99% completed project when all tasks are 100%

Home Forums Discussion 99% completed project when all tasks are 100% Reply To: 99% completed project when all tasks are 100%

#277693
David Rae
Guest

I have seen this and have found a solution, although I don’t understand the reason it is occurring. If you look at the “Actual Finish” field it shows as N/A. If you set this date the 99% changes to 100%.