Reply To: Assigning resources full time for a portion of the task

Home Forums Discussion Assigning resources full time for a portion of the task Reply To: Assigning resources full time for a portion of the task

#300799
Sai PrasadSai Prasad
Participant
  • Community Leader
  • Forum Pro

Harold – You can ask Project to respect the Start and Finish date by changing the Task Mode to Manually Scheduled. This will ensure as you increase/decrease work the start and finish won’t change. Now change your view to Task Usage (View ribbon). In Time-phased data (right side) enter the 8 hours for the first two days and make edits for the remaining days left.