Loading...
Quick Links

Reply To: Project 2013 – Sorting by date, duration etc not working in custom report

Home Forums Discussion Project 2013 – Sorting by date, duration etc not working in custom report Reply To: Project 2013 – Sorting by date, duration etc not working in custom report

#304072
Matt DD
Guest

Thanks a lot for your response Ismet.

I’ve just tried creating a copy of the project and sorting in the Gantt view rather than a report but it’s still not sorting in any meaningful order (although it is changing the order of the tasks).

Just tried on a different project template I downloaded from the internet and it worked fine on that so think it must be something about the data I’ve inputted.

Afraid I don’t know about the SP1 and cumulative update – I’ve got Project installed on a work computer so I assume it’s an up-to-date version.

Matt