Home › Forums › Discussion › Project 2013 – Sorting by date, duration etc not working in custom report › Reply To: Project 2013 – Sorting by date, duration etc not working in custom report
— Just in case, pls check the setting “Fiscal year starts in” on the Schedule tab of the Project Options dialog box. Is it January ?
— And also check the version information from the Account tab in Backstage (click File > Account | About Project). Let us see the whole version string (e.g. … 15.x.xxxx.xxxx SPx MSO …) to understand the update status of the product.
This is the Update Center for Office products: https://technet.microsoft.com/library/dn789213(v=office.14). It can be verified with the IT Dept. that whether they include Project updates in their update routine.
If you like, you can send me the file at ikocaman.pm[at]gmail.com.