Reply To: Aggregate lists across all project sites in PWA 2010

Home Forums Discussion Aggregate lists across all project sites in PWA 2010 Reply To: Aggregate lists across all project sites in PWA 2010

#305912
Larry Christofaro
Participant

Jennifer, There are a couple of things you can do. For Issues and Risks, these lists are synchronized to the reporting database and can be reported using Excel or SSRS. For other lists that are not out of the box with Project Server, you can use SharePoint content types with site columns. This is all SharePoint functionality. It is certainly an option but will require a bit of SharePoint expertise. Hope that helps…