Yep, should be simple…but of course the devil is in the details. Have you tried to export information to Excel using the export wizard? With the schedule open, select Save As, save as format Excel Workbook, and follow the wizard. Select Selected Data, Assignments, then select Task Name, Resource Name, Finish (or baseline finish if that’s what you want for due date), and whatever other fields you need. Now that it’s in Excel you can do what you want. You can even setup a standard map and Excel Macro for future exports. Hope that helps…