Home › Forums › Discussion › Custom Report by resource by date › Reply To: Custom Report by resource by date
Hi, Larry thank you so much this worked perfectly!
I have one more question, I am trying to make the Task Names export to Excel, i can do this through just copying and pasting however when i do this i lose the WBS code numbers. Is there anyway that I can export (or copy and paste) the task names whilst maintaining the wbs numbering?
Thanks in advance
Chris