Reply To: Avoiding using constraints in the Project Schedule

Home Forums Discussion Avoiding using constraints in the Project Schedule Reply To: Avoiding using constraints in the Project Schedule

#319172
Larry Christofaro
Participant

Alasdair, that’s actually a good question. Yes, using predecessors to dynamically schedule your project is “best practice”. There are a lot of best practices, and to use them all requires a pretty detailed level of managing projects. I’m not sure if your question is about a particular project or all your projects. Some projects just don’t work well using pure predecessors. Here’s some thoughts. If you are setting lag and lead just to get the successor task to start where you want it to then using a constraint is probably a better solution. If the successor task isn’t dependent on the predecessor task then using a constraint is definitely a better solution (although in reality something should driving each task). Just think about each situation. Here’s a thought, if you are managing projects without managing actual schedule (simply marking tasks as complete or not without regard to timeline), then set tasks up however you want. If that’s the case I would certainly encourage learning more about Microsoft Project, but there are many who manage that way. Hope that helps…