Reply To: Calendar – Working Hours – Reset

Home Forums Discussion Calendar – Working Hours – Reset Reply To: Calendar – Working Hours – Reset

#324726

Let us shorten the process:
– Locate Global.mpt in your system (path is C:\Users\<profile_name>\AppData\Roaming\Microsoft\MS Project\14\1033 for Project 2010 client in a Windows 7 system).
– Then rename Global.mpt to Global.old (thus you can revert to the original Global.mpt when things go wrong).

Project will create Global.mpt with the defaults again as soon as you start Project. Note that all the customizations in the original Global.mpt will be lost (you can transfer them to an mpp file before deleting the original Global.mpt).