I uninstalled and re-installed MS Project and I’m still seeing the problem with float values failing to recalculate after changing logic or lead/lag. Could this be an Office 2013 issue? A Windows 7 issue? It’s very frustrating because now I question the data that I’m seeing in MS Project. Float values that are way out of whack are obvious but I worry about the other errors that I may not be seeing.