Michael, is this happening with every project or just the consultant schedules? What product or version were the consultant schedules developed? One thought, install Project 2010 along side 2013. Microsoft certifies it works and I use them both all the time. Test a repeatable scenario on both and see if the problem is truly just with 2013. If the scenario happens only with 2013 then it’s a bug and should get reported. I haven’t heard of it but then I am not privy to the bug list. Good luck…