Larry Christofaro
Participant

Hi Sheila. Your question is certainly valid and is very typical. There are a couple of options available. There is a field in the Resource Usage view called Task Summary Name that you can add in front of the task name. That’s probably your best easy option. Because I personally don’t like the real-estate that the extra field creates, I instead tend to include enough description on a task to make sure it is distinguishable from other tasks. Given your specific example above I would create tasks as D1-Perform technical review and D2-Perform technical review. Hope that helps…