Ryan, unfortunately when you save a project from Project Server as a file (outside of Project Server) you get a new file. All of the link relationships will be disconnected. It’s hard to know what is causing the dates to move but a couple of possible causes could be (1) calendar differences or (2) predecessor relationships from the previous external links. Let us know if you find out the answer.