1. Auto-rejection of Status Updates with typical rejection comment: “The timesheet has been rejected because it contained at least one task that has been deleted or reassigned”.
The timesheets were approved and sent to SAP for processing and SAP has the data correct – however the Status Update was auto-rejected. So the EPM Project doesn’t get updated with the actual hours. So can any one give me the solution for why my Status shows as rejected ?