Home Forums Customization SS and FF relation to the same task? Reply To: SS and FF relation to the same task?

#349035
Sai Prasad
Participant
  • Community Leader
  • Forum Pro

Hi – In Project, you can’t set two dependency types between the same predecessor and successor. Alternate is have SS dependency and revise the duration of the successor every time the predecessor duration changes. Another alternative is don’t any dependency between A and B rather copy the start date of task A and paste it as link in Task B star column and do the same for finish date. For more information, visit https://support.microsoft.com/en-us/kb/141733