Home Forums Discussion Changing Project owner Reply To: Changing Project owner

#351850
Larry Christofaro
Participant

Darren, you can add the Owner field to one of the PDPs to show and change ownership. The problem you might run across based on your question is that a resource needs to have the permission to create projects in order to be able to be assigned as an owner. I tend to recommend creating a separate Project Manager field for assigning the project owner/manager and run reports off of that. Unless you need specific security permissions for the project owner/manager, I tend to find the workarounds difficult. Let me know if that solution doesn’t work.