Tun,
Welcome to Microsoft SharePoint and Project, and I hope you enjoy the trip. For number one: In Microsoft Project, go to File / Info / and you will see Map Fields next to the Save button. That is where you map fields between Project and SharePoint. Predecessors should synch, not sure why they wouldn’t. Let’s start with number one and see if that helps. Maybe that will also fix number two…??
Thanks…Larry