Reply To: How to: Bulk add group of tasks to multiple items at same time?

Home Forums Discussion How to: Bulk add group of tasks to multiple items at same time? Reply To: How to: Bulk add group of tasks to multiple items at same time?

#356773
Larry Christofaro
Participant

Steve,
I would enter the tasks (name only…probably) in Excel and then copy the tasks to Project. You have a lot more options in Excel to do things like merge and copy down that you don’t have in Project.
Hope that helps…