Reply To: Critical Path for a selected tasks in MS Project

Home Forums Discussion Critical Path for a selected tasks in MS Project Reply To: Critical Path for a selected tasks in MS Project

#359974
Larry Christofaro
Participant

Task path options are under the Format menu in the Gantt chart view. It shows all predecessors/successors and driving pred/succ depending on what you want highlighted. Hope that helps…