Loading...
Quick Links

Reply To: Adjusting durations of linked tasks.

Home Forums Discussion Adjusting durations of linked tasks. Reply To: Adjusting durations of linked tasks.

#361061
Thomas Boyle
Guest

Hello Kedar Pitre,
You are describing symptoms that are usually associated with small offsets in the clock-time entries you have made in the schedule.
Go to the General Options and choose a Date Format that shows clock time as well as the date.
You will then (typically) find that your 4-day task is scheduled to start 1 or 2 hours after the project’s scheduled start of work on Monday, and this offset will carry over to Friday.
To fix, check whether you have made an incorrect manual entry for a start-date somewhere in the schedule. Also check if you have a small offset between the project, task, and resource calendars – which can cause similar symptoms.
Good luch