Reply To: Hi all! Is there a possiblity to combine Fixed Work AND Fixed Duration?

Home Forums Discussion Hi all! Is there a possiblity to combine Fixed Work AND Fixed Duration? Reply To: Hi all! Is there a possiblity to combine Fixed Work AND Fixed Duration?

#362099
Larry ChristofaroLarry Christofaro
Participant

Mariska, the only way to truly guarantee this is to not change the task. The task can move as a result of predecessors or other factors that change the start date; but just don’t change the duration, units, or work (or assign additional people). If you leave it alone, Microsoft Project won’t change it by itself (assuming you don’t do anything advanced like use resource leveling, etc.). Hope that helps…