1. Unfortunately Microsoft executes a print function that doesn’t always print what you see on the screen. I use a different PDF writer that seems to do a better job of printing PDFs. You can search for PDF995 and get what I use. Please note that I got this ages ago and make no claim that this is the best option out there. It’s just something I’ve been using for like ever… There may also be other and better options for you.
2. My assumption is that something is amiss with your calendars. You have a calendar that is set to 10a-7p conflicting with an 8-5p calendar. Check the project calendar, task calendar, and resource calendars of the tasks in question.
Hope that helps…