Hi Mariska,
I believe using Fixed Duration task type with the Effort Driven field checked will accomplish what you are expecting. Microsoft Project will not recalculate duration if the task type is Fixed Duration and it will keep the work constant if the “Effort Driven” check box is checked, thus the only field Microsoft Project can recalculate is Units. Hope this is what you are looking for.