Reply To: Adjusting durations of linked tasks.

Home Forums Discussion Adjusting durations of linked tasks. Reply To: Adjusting durations of linked tasks.

#362214
Kedar Pitre
Guest

I corrected the calendar to 10am -7pm as per our company timings before feeding in rest of the information in the project schedule.
a) It shows the changed time as long as it is in Manual mode but if I click Auto Schedule the timing switches back to 8am – 5pm.
b) The resource schedule does not show the change in time or holidays, so do we have to manually feed in the changes for each resource(employee)?
c) Without Auto schedule, the task type cannot be changed and it remains on Fixed Units.
d) Is there a way to import the change schedule in the employee’s calendar?
e) Is there a way to change the standard calendar or add our calendar to the existing 3 – Standard, Night Shift and 24 hours.