Reply To: Adjusting durations of linked tasks.

Home Forums Discussion Adjusting durations of linked tasks. Reply To: Adjusting durations of linked tasks.

#362437
Kedar Pitre
Guest

Hi Larry

Thank you again for the quick response.How and where do I add a post for others to see? Would definitely like to assist others too.
I did put the calendar as you mentioned in the Global.For this I created a blank file and inserted all the holidays and other changes like we have a 6 day week. The new file (Project Template) can now be seen in Project – Information in a drop down as well as in Change working time under the Project Tab. But the holidays do not show on the Gantt chart which still shows a 5 day week and no holiday, when I open a new file.So how does one use the global Template?
Than