Reply To: Adjusting durations of linked tasks.

Home Forums Discussion Adjusting durations of linked tasks. Reply To: Adjusting durations of linked tasks.

#362525
Kedar Pitre
Guest

Hi Thomas n Larry,

You got it bang on – checked the Gantt chart and corrected it, so now the correct calendar is in effect everywhere!
Regarding my previous post – a, b, c, d. The problem was solved when I clicked on Project – Information and changed the calendar from Standard to the one I wanted. Ditto with Project – Change working time. in the resource sheet changed the calendar for each resource to the one I needed. This done all the problems was solved less the Gantt Chart which Thomas helped out with today!

Thanks a lot both of you. I couldn’t have got the solutions going through the myriad of books/videos searching for these specific problems!