Sai Prasad
Participant
  • Community Leader
  • Forum Pro

I agree with Larry. You can’t do it with Progress lines. The work around is hide the summary tasks in the Gantt Chart. You can create a filter (View tab > Filter drop down … New Filter) and copy the filter definition of Summary. In the Filter definition dialog, change the condition to “Summary equals No” and clear Show related summary tasks. Apply this new filter. It will display all tasks except summary tasks. Now apply the progress line on this view.