Loading...
Quick Links

Reply To: Task Pane Resource assignment behavior change since about July 2015

Home Forums Discussion Task Pane Resource assignment behavior change since about July 2015 Reply To: Task Pane Resource assignment behavior change since about July 2015

#369103
Larry ChristofaroLarry Christofaro
Participant

Response update, after quite a bit of playing around this is what I found out:
1. As stated, I had the same expected behavior with my Project 2010 version as you have been used to
2. Unfortunately I was unable to find an older Project 2013 version in which the expected behavior was consistent to Project 2010
2. I did find that the behavior using Project 2016 (preview version) produced the same results as Project 2010 and as expected.
So, my only conclusion is that there was a change a while back that caused a bug in Project 2013, and that the bug either was fixed or hasn’t been replicated in Project 2016. I wish I had better news but for now that’s what I know. I will probably post it on a Microsoft forum and see if anyone can confirm so stay tuned. Thanks…Larry