Reply To: Different Markup Rates on Different Resource Types

Home Forums Discussion Different Markup Rates on Different Resource Types Reply To: Different Markup Rates on Different Resource Types

#370249
Larry Christofaro
Participant

Ken,
Unfortunately Microsoft Project doesn’t do very well with this kind of requirement. Project is about costs, not billings or markups. You might be able to use cost rate tables if you know what you are doing but it is also a manual process. Best bet is to export to an Excel file and preconfigure or use macros to calculate margin. It’s actually not that hard if you spend some time to set it up. Hope that helps…