Reply To: Project Pro vs. Standard

Home Forums Discussion Project Pro vs. Standard Reply To: Project Pro vs. Standard

#372543
Larry Christofaro
Participant

Gary, wow I really thought I would just pass you on to a link that described the differences but that proved harder than I realized. Anyway, what Project Pro basically provides above and beyond Project Standard are the interface with Project Server/Online, synch to a SharePoint task list, and the Team Planner view. Team Planner is a drag and drop tool that allows you to manage resource assignments across project tasks. Some people like it a lot and some don’t I personally haven’t found it that useful for the way I manage projects. Hope that helps. If you are saying that Project Pro for O365 is cost equivalent to Project Standard then get the better product. If you aren’t using SharePoint at all then standard might be a viable option. Hope that helps…