Reply To: Using schedule templates / rolling wave planning

Home Forums Discussion Using schedule templates / rolling wave planning Reply To: Using schedule templates / rolling wave planning

#373770
Larry Christofaro
Participant

Jerry, this is certainly not a unique issue. Not using timesheets help as you can copy tasks from one project to another without too much trouble. You might try to insert a project but unlink the sub-project. This would take the template (as a project stored someplace) and copy under your planning tasks. Under the Project ribbon, choose Sub-Project. In the insert dialog box, unselect the Link to Project checkbox. Try that and let me know if that works. It might take a couple of tries to get it working right so start with a test project. If you have specific issues then respond again and let us know.

Should have thought of that the first time. I must have been too busy asking questions. Hope that helps…