Reply To: Having Project Not Include Non-Working Days in Lag Times?

Home Forums Discussion Having Project Not Include Non-Working Days in Lag Times? Reply To: Having Project Not Include Non-Working Days in Lag Times?

#377229

I’m new to MSProject, but I believe (in 2013 at least) you use Edays in the lag time instead of days (Edays refers to Elapsed Days and includes the days off)

for 2 weeks you could put 14ed or 2ew