Reply To: Having Project Not Include Non-Working Days in Lag Times?

Home Forums Discussion Having Project Not Include Non-Working Days in Lag Times? Reply To: Having Project Not Include Non-Working Days in Lag Times?

#377243
Larry Christofaro
Participant

Ken is corect, and available in any version (at least in this century…). The format is 1FS+14 ed (successor to task 1, FS, plus 14 elapsed days).