Home Forums Discussion Individual Project Managers in a Master Project Reply To: Individual Project Managers in a Master Project

#378108
Luvjit Kaur
Guest

Hi Randy,

Its been a while since you posted this question. You might have found the solution by now, if not then here it is. You have to select the subproject option in the project ribbon in project center view.