Larry,
My User has a project of about 200 steps which rely on on each other … each task’s dates/timing is based on predecessor task(s). Project does this naturally …
However, my user basically wants to do the reverse. Set the end date of the last task and have Project tell him the date to set the first task to.
I do not think Project can do that. I think he change the dates of the early tasks until the end date of the last task is what he needs. Your idea of changing the critical path tasks’ dates could speed things though.
Does this make more sense now?
Thanks
John