Reply To: PS 2013 – Change a user to become a resource only

Home Forums Discussion PS 2013 – Change a user to become a resource only Reply To: PS 2013 – Change a user to become a resource only

#380110
Larry Christofaro
Participant

Sabastian: That’s a good point as I didn’t realize the difference, but unfortunately I don’t believe there is a way to change this. I’m not saying this is the answer but I might suggest taking snapshots and managing this in reports as an option. One challenge with your solution is that all in-flight projects need to change to the new resource at that same date, even if a task is in-flight (to be accurate of course). By creating snapshots with the right resource custom fields you will be able to extract the move date for a custom report or scheduled extract. A little bit of investment might go a long way to a simplified solution. Just trying to help with an alternative is all. Hope that helps…