Reply To: Change the Color of a Cell when Task Complete

Home Forums Discussion Change the Color of a Cell when Task Complete Reply To: Change the Color of a Cell when Task Complete

#380728
Andy Forrester
Guest

daniel,
There is a standard filter called Completed Tasks.
You can set it as a Highlight Filter and set Highlight text to show green background
This will show all completed tasks cells as green