Reply To: Options for task split

Home Forums Discussion Options for task split Reply To: Options for task split

#380748
Larry ChristofaroLarry Christofaro
Participant

Kamlesh, it’s hard to tell what is happening but the resume date would be set for previously in-process tasks with remaining work, out to either the date specified in the update project or to a date constrained by predessessor tasks with remaining work. You might check to see if there are predessessors on those tasks and if that might be your problem. Otherwise please provide additional information. Hope that helps…