Reply To: Exporting resource unit timephased data to excel

Home Forums Discussion Exporting resource unit timephased data to excel Reply To: Exporting resource unit timephased data to excel

#380879
Larry Christofaro
Participant

Try adding the Percent Allocation detail style to the Resource Usage view. From the Resource Usage view, select Add Details form the Format ribbon. Find and add the Percent Allocation style. Roll up to Outline Level 1 (resource totals only). I hope this helps…