Reply To: Filter tasks on Timeline View

Home Forums Discussion Filter tasks on Timeline View Reply To: Filter tasks on Timeline View

#382595
Larry Christofaro
Participant

Lisa, I might suggest creating multiple timelines, one for each phase. Project 2016 provides the feature of having multiple timeline bars within the same timeline view. But, in 2010/2013 you can still create multiple timeline views. Each phase would be a separate timeline but they could be displayed together in a PowerPoint or other option. One thing to note, you don’t have the ability to say you want a timeline based on an entry in a custom field. Using a custom field to filter out tasks would be a nice way to easily filter to the phases, but you still have to manually add the filtered tasks to a timeline.
Hope that helps…