David, I have a couple of questions for you. First, if you are using Microsoft Project then you can do a hammock task, and if you are using Resource Center views for resource demand management then it shouldn’t be a problem. Second, I’m not sure what OLE (assuming you are referring to Object Linking and Embedding) becomes a problem. Again, my assumption is that as long as it is updated in the Project client then it isn’t a problem in PWA.
The short version I guess is to ask for more specifics on the particular issue and what you are trying to get around. Hammock tasks are not used that often so I may have never run across that issue before. Thanks…