Reply To: Change Project TimeScale on PWA

Home Forums Discussion Change Project TimeScale on PWA Reply To: Change Project TimeScale on PWA

#383683
Larry Christofaro
Participant

Hi John, sorry to say there is not a way to customize the timescale setting. The timescale does change as you zoon in and out to match the Gantt chart, but this is automatic and cannot be configured.