Reply To: Project ID … Seems to appeared

Home Forums Discussion Project ID … Seems to appeared Reply To: Project ID … Seems to appeared

#384396

Larry,

Time to challenge you again ! 🙂 I have investigated the PROJECT ID.

A Project ID automatically created when a project is created. As shown below, old projects are not retroactively assigned an ID. However, you can go in assign one.

Each Enterprise Project Type has its own counter which can be defined to include a number plus prefixes and post-fixes. Currently, we have two project types … Enterprise Project Type (the default) and Web Based Training.

Question 1 … Can my two project types use the same counter definition … say starting at 1, and then will PWA be smart enough to not create duplicate IDs across the project types?

Question 2 … I can assign an ID to projects created before this enhancement. I have not tried to enter an ID already in use. Is Project ID defined as requiring UNIQUE entries?

Thanks
John