Reply To: How To — What is the best way to replace a resource?

Home Forums Discussion How To — What is the best way to replace a resource? Reply To: How To — What is the best way to replace a resource?

#384627
Sai PrasadSai Prasad
Participant
  • Community Leader
  • Forum Pro

Alfred, I am able to replace the resource with another resource for both incomplete and completed tasks using the Assign Resources command in Resource tab. Even if the new resource is non working or doesn’t follow the same working time of the replaced resource, Project 2013 moves the actual hours and remaining hours to the new resource. Hope this helps