Reply To: Filtering, and also higlighting

Home Forums Discussion Filtering, and also higlighting Reply To: Filtering, and also higlighting

#384859
Sai Prasad
Participant
  • Community Leader
  • Forum Pro

Hi Nick, Larry is correct. If you want the second filter to be applied on the result of the first filter, then you should create a custom filter. Create a new filter with the condition of both these filters and apply the same. Check this picture on how to join to conditions using AND condition https://i.imgur.com/sPFJ74K.png