Reply To: Total Slack Displayed in days (with decimals) and weeks.

Home Forums Discussion Total Slack Displayed in days (with decimals) and weeks. Reply To: Total Slack Displayed in days (with decimals) and weeks.

#384890
Larry Christofaro
Participant

Good question. I did a quick test and it depends on how the task duration is entered. If the task duration is entered in weeks then the Total Slack is displayed in weeks. It behaved very consistently for me, and if I change the duration label the Total Slack label changes accordingly. Let me know if you are experiencing something different.