Reply To: MS Project 2013: Customizing Calendar View (filter to specific user)

Home Forums Discussion MS Project 2013: Customizing Calendar View (filter to specific user) Reply To: MS Project 2013: Customizing Calendar View (filter to specific user)

#385620

Hi Kim,
It depends upon how you’ve “pulled” their schedules into yours. Take a look at the resource sheet in the master project – does each resource appear more than once? If so, you’ve inserted the projects as linked projects. To get Project to combine multiple instances of “Kim” in each project into one – create a new blank project and insert each project without linking. (Uncheck the “Link to Project” checkbox in the Open dialog. You are not linked to the original files so you’d need to re-create the master project for reporting.

I hope this helps.

Julie Sheets
Project MVP