Hi Bob,
Have you thought about using a cost resource instead? You can assign a cost resource and specify the cost at each assignment. I don’t 100% follow setting the duration to 10 months (for example) for a monthly charge. Consider setting up a milestone (can be manually scheduled) for either the start or end of the month. Create the cost resource and when you assign you enter the cost for the fee on a monthly basis.
Does that help?